We are currently estimated to be 25% through with Phase III of the reconstruction on the Manitou Incline. Our focus at the beginning of the project has been to get the proper supplies to the trail (via helicopter) and to remove old drainage culverts and unsafe steps.
To date, we have started 4 of the 17 total retaining walls and 5 of the 11 water chases.
Since the trail is so steep, crews had to dig out flat areas next to the steps in order to create flat spots for the helicopter to drop items such as concrete, timbers, and metal pipes. Each load is carefully weighed to ensure that we are carrying a safe amount, while also maximizing each trip that the helicopter takes. The trail is marked to indicate where specific items will be placed to avoid having to carry heavy materials up or down the Incline.